DSME Lays Keel for Petronas’ First Floating LNG Facility

Post date: 08.01.2014 , Views: 286
Home > Maritime news > DSME Lays Keel for Petronas’ First Floating LNG Facility...
DSME Lays Keel for Petronas’ First Floating LNG Facility
The first block of the keel, the basic structure around which the hull of the FLNG vessel will be built, was laid on 6 January in the presence of the integrated project team led by PETRONAS with its partners, Technip and DSME.
“The keel laying signifies yet another significant achievement of the project in its construction phase,” said Datuk Abdullah Karim, PETRONAS’ Vice President and Venture Director of LNG Projects – Domestic, Gas & Power Business.
“We would like to thank the project teams for their perseverance and dedication that led to this milestone in a safe manner, in line with our plans and expectations,” he added.
The construction of the PFLNG 1 facility, which commenced in June 2013 with the cutting of the steel for its hull, is scheduled to be completed in Quarter 4 of 2015, making it the world’s first to be in operation.
When operational, the facility will have a weight of about 125,000 tonnes and is 365 metres in length, which is equivalent to three times the length of an NFL football field. It will also be the first to use the dual row cargo containment system to ensure limited sloshing within its hull.
The PFLNG 1 facility will be located in Malaysia’s Kanowit gas field, 180 kilometres offshore Sarawak. It will produce 1.2 million tonnes of LNG per year and will play a significant role in PETRONAS’ efforts to unlock the gas reserves in Malaysias remote and stranded fields currently deemed uneconomical to develop and evacuate.

Petronas, January 8, 2014

 